It will be spread across three distinct parcels, interconnected by aerial walkways, over a total construction area of 240,466 m². In the current project, this hospital will be able to accommodate approximately 879 patients (expandable to 1065 in contingency situations) and will provide a total of 2998 parking spaces, mostly covered.
Description of each parcel:
- Parcel A: The main hospital building, including all medical facilities, a car park and a helipad;
- Parcel B: Facilities dedicated to Mental Health and Rehabilitation units, administrative centre, outpatient services and parking areas;
- Parcel C: Building intended for Research and Education areas. This infrastructure will also feature a multi-storey car park.
All special installations associated with the project are included, as well as the exterior landscaping, to ensure appropriate environmental integration.
Key figures:
- Excavation: 472,100 m³
- Steel: 15,100 tonnes
- Concrete: 122,200 m³
- Formwork: 475,300 m²
- Piles: 19,900 linear metres
- Plasterboard walls: 287,000 m²
- Vinyl flooring: 112,300 m²
- Electrical cables: 850,000 lm (linear metres)
- Lighting fixtures: 25,000 units
- Interior paintwork: 350,900 m²
- Façades: 50,700 m²