Logo Mota Engil

Boavista Avenue:
Renewal

Porto, Portugal
Boavista Avenue Renewal
Client
Gestão Obras Públicas do Porto, EM.
Location
Porto, Portugal
Date
2013-2015
Status
Completed
Boavista Avenue, which stretches for around 5.5 kilometres, is the longest avenue in the city of Porto. It is home to some of the city's main attractions, such as Casa da Música and Parque da Cidade.
The Boavista Avenue renewal project extended over 2km.

Included work such as:

- Rehabilitation of wastewater, rainwater and water supply networks;

- Sidewalk redesign;                      

- Vehicle parking areas and circulation lanes;

- Recovery of electrical networks;                            

- Implementation of road markings and traffic signs;

- Earthworks within the construction area;            

- Paving of the avenue's roads.

The project process can be divided into 5 different specialties:

Pavements:

- Earthworks for pavement preparation;

- Improvement of surface characteristics by removing and replacing existing pavement layers;

- Laying cube and micro-cube paving stones.

Water supply/drainage networks:

- Replacement/repair of rainwater drainage systems;

- Replacement/repair of sanitation systems;

- Replacement/repair of water supply networks.

Signs:

- Installation and replacement of vertical signage (traffic signs);

- Restoration of horizontal signage (road marks) in sections where pavement works were carried out;

- Installation and replacement of traffic lights and illuminated signs.

Cross-section profile:

In the section where the redevelopment took place, Avenida da Boavista features a cross-section profile with two carriageways, each having two lanes per direction, sometimes including an additional parking area.

Pavement Structure:

The pavements of IC1 were constructed over the existing pavement, with the following structure:

- 6.0 cm – Wearing course in bituminous concrete;

- 7.0 cm – Binder course in dense bituminous concrete AC20;

- 9.0 cm – Bituminous macadam AC20;

- 30.0cm – Bituminous base course (with specific grading);

- Total – 22.0 cm in bituminous mixtures.

What´s next

Projects where the future takes shape